If you plan to demolish a building, or a part of a building, then you must provide us with a demolition notice.
We need at least 6 weeks notice.
Apply to demolish a building
(PDF, 130 KB)
We need to know:
- what is being demolished
- who is doing the demolition
- who owns the building
- the details of the person arranging the demolition
We also need a location plan of the building or structure (1:1250 scale preferred), showing the area where the work is being done.
You may be liable to a fine, if you fail to submit the appropriate notice.
Other things to do
You may also need to:
What happens next
Once we receive a demolition notice, we will carry out a site survey to make sure the demolition process is handled correctly.
Demolition work can cause problems for road users and neighbours or businesses in close proximity to the site.
Dangerous buildings